Friday, October 11, 2013

1/3 of the time

A third of the time of the contract period of 24 months - that's how much time we've gone through thus far and the work is about 10% done as per schedule. It is quite normal for any project to have a slow beginning period, but now we have about 85% progress that needs to be achieved for the whole of next year. It will be a very busy year for the contractors as well as us. The past two weeks has seen slow progress though some work managed to get done. I thought we should move faster and I think it can be done.
MLT for 800mm dia bored pile with working load of 270t